• Asbestos contaminated materials in demolition
• Airport activity to stay live throughout works
• Working airside meant being sensitive to strict protocols set by airport
Scope of Works
Demolition – 25,000m2 of road surface, 12,000m2 of clearing
Bulk Earthworks over site
Pavements
Carparks – 25,000m2 of sealed carpark
Kerb – over 3,000m installed
Linemarking and signs
Stormwater – over 500m of RCP supplied and installed, as well as over 30 pits
Hydraulics
Sewer – over 1.5km
Water – over 1.8km
Fire – over 1.1km
Installation of allied pump supplied materials and associated tie-ins
Grundfos Variable speed pressure system with remote monitoring Hydrokos15
2 of heavy-duty steel circular potable water storage tank – 43kl each
2 of heavy-duty steel circular fire water storage tank – 108kl each