Esperance Bus Depot – Programmed Facilities Management
Project Description
Construction scheduling around inclement weather.
Optimising asphalt/concrete pavement layout to achieve cost effective solutions.
Locating and working with and around a labyrinth of unmarked services, clearing
and relocating these as required
Scope of Works
Rework of existing ground
surface, and construct the
required contours
Asphalt the entire yard to all
areas indicated in the supply
drawings
Supply, install and commis
Supply and install concrete pads for the
diesel tank, and plate separator and
fuelling bay with bunding
Relocate fuel tank
Supply and install 3000L plate separator
Supply and install crossover
Supply and install 8m wide manual gate
Remove and replace of Cyclone and Colourbond style fencing