Project Description

Construction scheduling around inclement weather. Optimising asphalt/concrete pavement layout to achieve cost effective solutions. Locating and working with and around a labyrinth of unmarked services, clearing and relocating these as required

Scope of Works

  • Rework of existing ground surface, and construct the required contours
  • Asphalt the entire yard to all areas indicated in the supply drawings
  • Supply, install and commis
  • Supply and install concrete pads for the diesel tank, and plate separator and fuelling bay with bunding
  • Relocate fuel tank
  • Supply and install 3000L plate separator
  • Supply and install crossover
  • Supply and install 8m wide manual gate
  • Remove and replace of Cyclone and Colourbond style fencing